|
Status Report 10/21/99
Project Purpose:
To remove nutrient enriched sediment (organic muck) from Lake Jackson during naturally low
water levels. The muck that has accumulated in Lake Jackson is the result of
stormwater runoff discharges from developed areas of the watershed.
Implementation Status
The muck removal project is being implemented in two phases. The initial phase is
currently underway and entails muck removal in Meginniss and Fords Arms in the southern
portion of the lake. These areas have the highest nutrient concentrations due to
their proximity to major stormwater discharge conveyences from the Tallahassee urban area.
Phase II is currently in the design and permitting stage and all necessary
approvals are expected by the end of November 1999.
Meginniss Arm
|
|
|
|
Project Management: |
|
Leon County |
Amount of Muck: |
|
175,000 cubic yards over approximately 104 acres |
Current Status: |
|
Muck being stockpiled; hauling from lake will begin by 11/1/99 |
|
Cost: |
|
Approximately $1.25 million - $300,000 for sediment dewatering, access
construction and stockpiling and approximately $954,000 ($5.45 per cubic yard) for hauling
and disposal at remote locations. |
Issues: |
|
Higher cost is due to long distance hauling of the muck (to west side of
Tallahassee) |
Fords Arm
|
|
|
Project Management: |
|
Florida Fish and Wildlife conservation Commission |
Amount of Muck: |
|
150,000 cubic yards over approximately 37 acres |
Current Status: |
|
Approximately 1/3 Complete |
Cost: |
|
Approximately $174,000 or $1.16 per cubic yard |
Issues: |
|
Lower cost is because the disposal area location is close enough to the
work area to use large-capacity off-road dump trucks. Additional disposal area may
be needed to complete Fords Arm work. Increased distance to disposal areas will
increase project cost. If FWC funding is not adequate to meet additional cost, a
budget amendment will need to be expedited to allow FWC receive and expend available funds
from Leon County. |
Phase II
Status - Phase II will involve the southern portion of Lake Jackson
outside of the Phase I area, with the initial priority being the areas immediately
adjacent to Meginniss and Fords arms. Planning level calculations indicate the Phase
II could involve over 500 additional acres of lake bottom with sediment quantities in
excess of 1.5 million cubic yards.
Funding - Because the designs are not complete, it is difficult to
provide specific quantities of muck to be removed in Phase II. It is also difficult
to accurately estimate cost before all of the logistics concerning disposal sites, project
dewatering needs, and equipment requirements are known. The best current estimate is
that approximately $2.5 to $3 million in additional funding is needed to
complete a significant amount of Phase II. However, funding in smaller amounts can
be used, since the project can be completed incrementally as funds become available.
Important Issues:
|
Funding: |
|
Leon County: $2,000,000 (Muck Removal)
FWC: $150,000 (Muck Removal)
NWFWMD Approx. $100,000 (Design, Permits, Sediment Analysis, Coordination)
FDEP: Approx. $20,000 (Sediment Analysis)
|
|
Timing: |
|
Sustained wet weather will cause the lake to refill and the project to be
discontinued.
The last natural drawdown lasted only four months; however, previous dewatering events
have lasted more that 9 months
|
|
Sediment Quality: |
|
The sediment targeted for removal from the lake is enriched with nutrients
(nitrogen and phosphorous) at levels that upset aquatic ecosystems by causing excessive
plant growth, including algae blooms. While harmful in an aquatic system, the levels
of nutrients in the muck are not harmful if applied to the land surface. Testing of
the muck for heavy metals and pesticides has revealed that no special handling or disposal
is required.
|
|
Stormwater Runoff: |
|
A coordinated effort is currently underway to capture and treat stormwater
runoff before it enters the lake. Five regional stormwater treatment facilities have
been constructed and four additional regional facilities are planned and budgeted for
construction. |
Project Partners
Lake Jackson Designations
- Outstanding Florida Water (OFW)
- State Aquatic Preserve
- Surface Water Improvement and Management (SWIM) Priority Waterbody
- Florida Nonpoint Source Pollution Priority Waterbody (U.S. EPA designation)
Economic Value of Lake Jackson
An economic study of Lake Jackson was completed in 1995. This study, titled: The
Economic Value of Lake Jackson, was prepared by the A.L. Burruss Institute of Public
Service of Kennesaw State College and the Florida State University Department of
Economics. The report indicates that in Leon County, Lake Jackson generated
about $10.6 million in lake-related purchases in 1993, and that this spending created
about $1.9 million in wages, supporting 96 jobs in the county.
It should be noted that the surveys that formed the basis of this study were
administered during a time when the level of Lake Jackson was low enough to severely limit
access to the lake. Thus, many lake managers in the area regard the economic values
reported in this study to be quite conservative.
|